Rue du Charroi 21–23

Forest · 07/IPEPLP/548034 · Prolongation de PE

Rue du Charroi 21–23, Forest: operation of installations. Case annulé, lodged on 12 September 2014. The decision was notified on 19 March 2015, 188 days after lodging.

exploitation d'un poste de transformation 150/36/11 kV : prolongation de 2 transformateurs statiques à l'huile minérale de 50 mVA
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusAnnulé
Lodged on12 September 2014date the file was received
Decision notified19 March 2015188 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.