Withdrawn
Rue du Charroi 21–23
Forest · 07/IPEPLP/548034 · Prolongation de PE
Rue du Charroi 21–23, Forest: operation of installations. Case annulé, lodged on 12 September 2014. The decision was notified on 19 March 2015, 188 days after lodging.
exploitation d'un poste de transformation 150/36/11 kV : prolongation de 2 transformateurs statiques à l'huile minérale de 50 mVA| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 12 September 2014 | date the file was received |
| Decision notified | 19 March 2015 | 188 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)