Granted
Boulevard de l'Humanité
Forest · 07/IPEPLP/661129 · Prolongation de PE
Boulevard de l'Humanité, Forest: operation of installations. Case octroyé, lodged on 4 January 2018. The decision was notified on 17 January 2019, 378 days after lodging.
L’exploitation d’un parc à conteneurs - Prolongation| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 January 2018 | date the file was received |
| Decision notified | 17 January 2019 | 378 days |
| Works started | 18 January 2019 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 59 m | Demolition and reconstruction | Démolir et reconstruire un kot Recupel et d'un préau | 2023 |
| 116 m | Public space | Installer un panneau de guidage dynamique pour le P+R CERIA sur le Ring 0 à hauteur du km 58.35 | 2023 |
| 197 m | Signs and advertising | Placer un dispositif de publicité type monopied double-face de 8m², rétroéclairé | 2021 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)