Skip to content
AltUrb
Granted

Rue Béranger 9

Forest · 07/IPETMP/2036921 · Permis d'environnement temporaire

Rue Béranger 9, Forest: energy works. Case octroyé, lodged on 25 June 2026. The decision was notified on 17 July 2026, 22 days after lodging.

Verwijderen van gips isolatie in kelder van een particuliere woning
The application's own description, in its source language (NL). Source: Nova.
Key figures
Permit typePermis d'environnement temporaire
StatusOctroyé
Lodged on25 June 2026date the file was received
Decision notified17 July 202622 days
Works started27 August 2026
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted
  4. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
18 mHeavy renovationmodifier répartition intérieure des 8 logements et mettre en conformité la modification de la façade avant (châssis)2024
27 mFaçade and windowsModifier des baies de fenêtres en façade arrière et agrandir une baie dans un mur porteur intérieur2022
30 mTree fellingAbattre 1 arbre à haute tige2024
40 mExtension or raisingmettre en conformité la construction d’annexes au rez-de-chaussée et au 2ème étage, l’imperméabilisation de la zone de c2026
43 mExtension or raisingaménager une terrasse arrière au 2ème étage2024

Other nearby cases : 07/PU/1900239, 07/PU/1859387, 07/SFD/1901157, 07/PU/1830730, 07/PU/1945268, 07/PU/2028828, 07/PU/1941751, 07/PU/1957184, 07/PU/1908626, 07/PU/1852715, 07/PU/1840305, 07/PU/1907214, 07/PU/1906635, 07/PU/1911325, 07/PU/1904784, 07/SFD/1967659, 07/PU/1916783, 07/PU/1977096, 07/PU/1846923, 07/PU/2011912, 07/SFD/1810810, 07/PU/2023494, 07/PFU/1949143, 07/PU/1865286, 07/PFU/1800036

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)