Granted
Rue du Curé 15–29
Forest · 07/PFD/110687-01 · Permis d'urbanisme délivré par le FD
Rue du Curé 15–29, Forest: new construction. Case octroyé, lodged on 25 March 1997. The decision was notified on 19 August 1997, 147 days after lodging. It comprises 30 dwellings.
construire un immeuble de 30 logements (R+4) avec garage en sous-sol (11E)30
Dwellings created
| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 25 March 1997 | date the file was received |
| Consultation committee | 8 July 1997 | |
| Decision notified | 19 August 1997 | 147 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)