Boulevard de l'Humanité, Forest: new construction. Case octroyé, lodged on 15 February 2002. The decision was notified on 9 April 2002, 53 days after lodging.
construction d'un poste haute-tension en gare de Forest-Midi| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 February 2002 | date the file was received |
| Decision notified | 9 April 2002 | 53 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)