Chemin d'Accès, Forest: public space. Case octroyé, lodged on 6 January 2003. The decision was notified on 18 March 2003, 71 days after lodging.
démolir et renouveller la sous-station de transformation pour alimenter la ligne de tram 54.| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 6 January 2003 | date the file was received |
| Decision notified | 18 March 2003 | 71 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)