Granted
Rue du Charroi 21–23
Forest · 07/PFD/1787191 · Permis d'urbanisme délivré par le FD
Rue du Charroi 21–23, Forest: energy works. Case octroyé, lodged on 20 May 2021. The decision was notified on 19 July 2021, 60 days after lodging.
Démanteler le transformateur
Mettre en place un nouveau transformateur
Mettre en place un nouveau groupe électrogène de secours
Remplacer les trois batteries
Mettre en place le nouveaux mâts paratonnerre
Adapter le réseau d'égouttage| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 20 May 2021 | date the file was received |
| Decision notified | 19 July 2021 | 60 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Tree felling | Abattre 34 arbres d'un poste haute tension pour objectif de sécuriser les installations électriques et les personnes. | 2022 |
| 5 m | Other | Réaliser des travaux techniques dans l'enceinte du poste électrique (ajout d'équipements techniques). | 2026 |
| 207 m | Change of use | Transformer un site existant (composé d’un ancien entrepôt, d’une maison de maître et d’une annexe) et de sa cour actuel | 2024 |
| 220 m | Change of use | Mettre en conformité la modification de destination du bien d'atelier (activité productive) en car-wash (commerce) | 2025 |
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)