Granted
Rue du Charroi
Forest · 07/PFD/236691 · Permis d'urbanisme délivré par le FD
Rue du Charroi, Forest: new construction. Case octroyé, lodged on 22 September 2009. The decision was notified on 17 March 2010, 176 days after lodging.
Construire une sous station de traction de 25 kv| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 22 September 2009 | date the file was received |
| Decision notified | 17 March 2010 | 176 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.