Granted
Rue du Charroi
Forest · 07/PFD/403297 · Permis d'urbanisme délivré par le FD
Rue du Charroi, Forest: new construction. Case octroyé, lodged on 3 May 2011. The decision was notified on 26 May 2011, 23 days after lodging.
Construire un poste à haute tension sur la zone de chemin de fer comprise entre la rue du Charroi, la rue Saint-Denis, et le boulevard de l¿Humanité.| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 3 May 2011 | date the file was received |
| Decision notified | 26 May 2011 | 23 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)