Avenue du Pont de Luttre 134–140

Forest · 07/PFD/474424 · Permis d'urbanisme délivré par le FD

Avenue du Pont de Luttre 134–140, Forest: new construction. Case octroyé, lodged on 30 August 2012. The decision was notified on 31 July 2013, 335 days after lodging. The project creates 100 m² of housing.

Construction d'un complexe d'équipements de proximité dans le cadre d'un contrat de quartier
The application's own description, in its source language (FR). Source: Nova.
100
Housing floor area created
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on30 August 2012date the file was received
Public inquiry26 February 2013 – 13 March 2013
Consultation committee26 March 2013
Decision notified31 July 2013335 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.