Granted
Rue Bollinckx 319–325
Forest · 07/PFD/487920 · Permis d'urbanisme délivré par le FD
Rue Bollinckx 319–325, Forest: demolition and reconstruction. Case octroyé, lodged on 30 May 2013. The decision was notified on 17 October 2013, 140 days after lodging.
Mettre à niveau la station d’épuration de Bruxelles Sud. Démolir et reconstruire des enveloppes conformément aux exigences technologiques et aux normes européennes.| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 May 2013 | date the file was received |
| Decision notified | 17 October 2013 | 140 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)