Chaussée de Bruxelles 24

Forest · 07/PFU/281894 · Permis d'urbanisme unique délivré par le FD

Chaussée de Bruxelles 24, Forest: public space. Case octroyé, lodged on 30 April 2010. The decision was notified on 23 February 2011, 299 days after lodging.

Remplacer des canalisations de gaz naturel.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme unique délivré par le FD
StatusOctroyé
Lodged on30 April 2010date the file was received
Consultation committee11 January 2011
Decision notified23 February 2011299 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Consultation committee
  5. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
48 mTree fellingAbattre 6 arbres presque mort ou en mauvais état dans diverses voiries , en cours d'abattage / dessouchage pour replanta2024
49 mHeavy renovationRestaurer l'église Saint-Denis2023
49 mOtherMettre en lumière l'église Saint-Denis à Forest suivant dossier descriptif des travaux2022
49 mHeavy renovationRestaurer l'église Saint-Denis2022
81 mPublic spaceRéaménager l'aire de jeux des jardins de l'abbaye de Forest2023

Other nearby cases : 07/PFU/1959980, 07/PFU/1925220, 07/PFU/1924431, 07/PFU/1864454, 07/PFU/1961952, 07/PFU/1863442, 07/PFU/1947331, 07/PFU/1943450, 07/PFU/1904011, 07/PFU/1892601, 07/PFU/1904145, 07/PFU/1835350, 07/PFU/1843944, 07/PFU/1849432, 07/PFU/1976774, 07/PFU/2033859, 07/PU/1825480, 07/PFU/1911048, 07/PFU/2037537, 07/PFU/2032043, 07/PFU/2020312, 07/PFU/1990586, 07/PU/1929753, 07/PFU/2022124, 07/PFD/1944981

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)