Rue Bollinckx 267

Forest · 07/PU/1860135 · Permis d'urbanisme privé

Rue Bollinckx 267, Forest: change of use. Case octroyé, lodged on 2 November 2022. The decision was notified on 21 October 2024, 719 days after lodging. It removes 253 m² of office space.

Modifier une partie du complexe industriel en un commerce HORECA
The application's own description, in its source language (FR). Source: Nova.
253
Office floor area removed
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on2 November 2022date the file was received
Public inquiry10 September 2024 – 25 September 2024
Consultation committee8 October 2024
Decision notified21 October 2024719 days
Competent authorityForest

Timeline

  1. Application lodged
  2. Public inquiry opened
  3. Public inquiry closed
  4. Consultation committee
  5. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
73 mRoofRénover, isoler la toiture et installer un garde-corps pour la sécurité de l’équipe d’entretien de la toiture et de ses 2024
80 mDemolitionDémolition d'un appentis adjacent à des hangars existant.2025
97 mOtherMettre en conformité l'installation d'une clôture et utiliser un terrain pour stocker des conteneurs vides2022
111 mChange of useMettre en conformité la construction d'un volume central et la réalisation d'emplacements de stationnement et modifier l2022
111 mRetail or horeca fit-outMettre en conformité la construction d'un volume central et la réalisation d'emplacements de stationnement et modifier l2022

Other nearby cases : 07/PU/2003993, 07/PFD/2003755, 07/PU/2031702

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)