Rue de l'Eglise Saint-Martin 29

Ganshoren · 08/IPEPLP/675310 · Prolongation de PE

Rue de l'Eglise Saint-Martin 29, Ganshoren: operation of installations. Case octroyé, lodged on 3 April 2018. The decision was notified on 26 July 2018, 114 days after lodging.

exploiter l'atelier de menuiserie communal
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on3 April 2018date the file was received
Decision notified26 July 2018114 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mRoofIsoler des toitures par l’extérieur (14 cm PIR) avec végétalisation extensive tout en maintenant la membrane asphaltique2022
26 mSplit into dwellingstransformer et diviser une maison unifamiliale en deux maisons unifamiliales2021
38 mChange of usemettre en conformité le changement de destination (commerce > logement) et l'augmentation du nombre de logements2023
63 mExtension or raisingconstruire un logement supplémentaire sur deux niveaux en façade avant d’un immeuble de rapport existant2025
69 mHeavy renovationmettre en conformité des transformations divers2022

Other nearby cases : 08/PU/2004495, 08/PU/1838636, 08/PU/2041444, 08/PU/1933192, 08/PU/1988581, 08/PU/1899619, 08/PU/1966632, 08/PFD/1842263, 08/PU/1892213, 08/PU/1965627, 08/PFD/1844138, 08/PU/1899038, 08/PU/1931512, 08/PU/1922452, 08/PU/1857970, 08/PU/1994914, 08/PU/2002167, 08/PU/1833308, 08/PU/1894695, 08/PU/2015064, 08/PU/1908455, 08/PU/1839808, 08/PU/1855373, 08/PU/1855408, 08/PU/1936459