Granted
Rue au Bois
Ganshoren · 08/PFU/1967737 · Permis d'urbanisme unique délivré par le FD
Rue au Bois, Ganshoren: public space. Case octroyé, lodged on 19 December 2024. The decision was notified on 28 January 2025, 40 days after lodging.
Verbeteren van wegen en beheer van recratief gebruik.| Permit type | Permis d'urbanisme unique délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 December 2024 | date the file was received |
| Decision notified | 28 January 2025 | 40 days |
| Works started | 20 October 2025 | |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 36 m | — | Installer 4 panneaux d'information – un à chaque entrée principale Nous souhaitons également installer 4 barrières fores | 2026 |
| 54 m | Public space | Réaliser un curage d’entretien du lit du Molenbeek et de l’Overslagbeek conformément au plan de gestion N2000 prévu dans | 2024 |
| 67 m | Tree felling | abattage d'arbre.Une analyse des arbres situés au sud de celui-ci a révélé que 53 arbres posaient des problèmes de sécur | 2026 |
| 224 m | Regularisation | mettre en conformité une maison unifamiliale | 2023 |
| 226 m | Façade and windows | Le projet consiste à remplacer les garde-corps des balcons, les plaques de polymères des portes d’évacuation séparant le | 2025 |
Other nearby cases : 08/PFD/2001594
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)