Granted

Rue François Beeckmans 18

Ganshoren · 08/PU/1853844 · Permis d'urbanisme privé

Rue François Beeckmans 18, Ganshoren: merger of dwellings. Case octroyé, lodged on 6 September 2022. The decision was notified on 3 May 2023, 239 days after lodging.

mettre en conformité la modification du nombre de logements (unifamilial)
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on6 September 2022date the file was received
Decision notified3 May 2023239 days
Floor areasnot reported by the source
Competent authorityGanshoren

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
6 mFaçade and windowsremplacer le châssis au rez-de-chaussée2025
6 mExtension or raisingmettre en conformité une annexe arrière2023
11 mHeavy renovationréaliser des travaux de stabilité et d'isolation2021
37 mChange of usechanger la destination d'un rez-commercial en commerce horeca2026
38 mExtension or raisingmettre en conformité la fermeture de deux balcons en façade arrière2023

Other nearby cases : 08/PU/1926641, 08/PU/1851153, 08/PU/1858460, 08/PU/1944374, 08/PU/1936235, 08/PU/1929450, 08/PU/1846062, 08/SFD/1961109, 08/PU/2029448, 08/PU/1943604, 08/PU/1916062, 08/PU/1824617, 08/PU/1851590, 08/PU/2028134, 08/PU/1896108, 08/PU/1891746, 08/PU/1863982, 08/PU/1821213, 08/AA/1821194, 08/PU/1899023, 08/PU/1898236, 08/PU/1895778, 08/PU/1829856, 08/PU/1978338, 08/PU/1966634

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)