Rue César Franck 25–A-B
Ixelles · 09/C_PLP/1986595 · Prolongation de PE Communal
Rue César Franck 25–A-B, Ixelles: operation of installations. Case octroyé, lodged on 15 May 2025. The decision was notified on 13 November 2025, 182 days after lodging.
Utilisation d'un parking couvert| Permit type | Prolongation de PE Communal | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 15 May 2025 | date the file was received |
| Decision notified | 13 November 2025 | 182 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 25 m | Split into dwellings | mettre en conformité les modifications des gabarits et des baies, la division d'un duplex en deux logements et la mise e | 2023 |
| 25 m | Heavy renovation | mettre en conformité les modifications des gabarits et des baies arrière, la division d'un duplex en deux logements et l | 2021 |
| 38 m | Extension or raising | régulariser les travaux intérieurs et extérieurs réalisés non conformément au pu n°2014/465-120/72 notamment la rehausse | 2022 |
| 41 m | Change of use | changer l’affectation du bâtiment en fond de parcelle en logement | 2025 |
| 45 m | Façade and windows | isoler les pignons et la façade à rue au 4ème étage et rénover la terrasse avant | 2022 |
Other nearby cases : 09/PU/1841718, 09/PU/1948392, 09/PU/2034066, 09/PU/1928130, 09/PU/1949028, 09/PU/1825678, 09/PU/2028576, 09/PU/2029162, 09/PU/2016452, 09/PU/2016451, 09/PU/1953172, 09/PU/1844625, 09/PU/2037782, 09/PU/1867250, 09/PU/1838378, 09/SFD/1820273, 09/PU/1915945, 09/PU/2044550, 09/PFD/2004863, 09/PU/1984800, 09/PU/1840551, 09/PFD/1845364, 09/PU/1835694, 09/PU/1906147, 09/PU/2011048
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)