Withdrawn
Sous-station Uruguay
Ixelles · 09/IPE/448436 · Permis d'environnement
Sous-station Uruguay, Ixelles: operation of installations. Case annulé, lodged on 5 May 2006.
Exploitation de la sous-station Uruguay comprenant deux transformateurs statiques de type sec de 100 kVA et 1690 kVA (148,b).| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 5 May 2006 | date the file was received |
| Public inquiry | 12 June 2006 – 13 June 2006 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)