Withdrawn
Boulevard du Triomphe
Ixelles · 09/IPE/542712 · Permis d'environnement
Boulevard du Triomphe, Ixelles: operation of installations. Case annulé, lodged on 27 June 2014. The decision was notified on 2 July 2014, 5 days after lodging.
099B1&30569B1| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 27 June 2014 | date the file was received |
| Decision notified | 2 July 2014 | 5 days |
| Works started | 1 July 2014 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Works started
- Decision notified · Withdrawn
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)