Avenue des Saisons 94
Ixelles · 09/IPEPLP/1742653 · Prolongation de PE
Avenue des Saisons 94, Ixelles: operation of installations. Case octroyé, lodged on 19 February 2020. The decision was notified on 22 November 2021, 642 days after lodging.
Uitbating van een slagerij
| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 19 February 2020 | date the file was received |
| Decision notified | 22 November 2021 | 642 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 35 m | Office conversion | changer affectation du 1er étage de logement et bureaux en logement (5 studios et 2 appartements 2 chambres) | 2024 |
| 35 m | Change of use | changer l'affectation du 1er étage de 4 logements et 1 bureau en 7 logements (5 studios et 1 appartement 2 chambres et | 2024 |
| 47 m | Heavy renovation | transformer et rénover le bâtiment avant notamment démolir l’annexe du rez-de-chaussée en infraction, aligner le volume | 2026 |
| 53 m | Roof | agrandir une lucarne existante, en façade avant | 2021 |
| 58 m | Extension or raising | réunir deux logements pour en faire une maison unifamiliale, avec reconstruction d'une annexe arrière, ajout d'une lucar | 2024 |
Other nearby cases : 09/PU/2023414, 09/PU/1975924, 09/PU/1939021, 09/PU/1915945, 09/PU/1956535, 09/PU/1996699, 09/PU/1931737, 09/PU/1864725, 09/PU/1949566, 09/PU/1848670, 09/PU/1962741, 09/PU/2026719, 09/PU/2032820, 09/PU/2016973, 09/PU/1821225, 09/PU/1949028, 09/PFD/1924445, 09/PU/2037782, 09/PU/1855649, 09/PU/1845801, 09/PU/1983653, 09/PU/1904719, 09/PU/1800204, 09/PU/2044550, 09/PU/1969248
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)