Rue de l'Automne 38–42
Ixelles · 09/IPEPLP/589555 · Prolongation de PE
Rue de l'Automne 38–42, Ixelles: operation of installations. Case octroyé, lodged on 7 January 2016. The decision was notified on 3 January 2017, 362 days after lodging.
Demande d’exploitation d’une imprimerie et de dépôts pour la commune d’Ixelles| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 7 January 2016 | date the file was received |
| Decision notified | 3 January 2017 | 362 days |
| Works started | 9 January 2017 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 50 m | Façade and windows | mettre en conformité la façade avant | 2022 |
| 50 m | Façade and windows | mettre en conformité la façade avant | 2021 |
| 62 m | Heavy renovation | mettre en conformité le réaménagement des appartements aux 1er et 2ème étages et du duplex au 3ème étage et combles, ain | 2022 |
| 68 m | Change of use | régulariser le changement d'affectation de l'arrière bâtiment d'atelier en logement, la rehausse de cet bâtiment arrière | 2022 |
| 68 m | Change of use | régulariser le rez-de-chaussée des bâtiments avant et arrière notamment le changement d'affectation de l'arrière bâtimen | 2024 |
Other nearby cases : 09/PU/1909520, 09/PU/2013628, 09/PFD/2019248, 09/PFD/1982344, 09/PU/2028576, 09/PU/1865852, 09/PU/1992485, 09/PU/1928130, 09/GOU_PU/1998046, 09/PU/1935510, 09/PU/1844114, 09/PU/1949028, 09/PU/1801067, 09/PU/1826085, 09/GOU_PU/1824482, 09/PU/2026719, 09/SFD/1836650, 09/PU/1863054, 09/PU/1841718, 09/PU/2010711, 09/PU/1962741, 09/PU/1915945, 09/PU/1931737, 09/PU/1906147, 09/SFD/1826494
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)