Rue du Mail 50, Ixelles: —. Case octroyé, lodged on 8 May 2017. The decision was notified on 1 March 2018, 297 days after lodging.

Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on8 May 2017date the file was received
Decision notified1 March 2018297 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
1 mRetail or horeca fit-outRéaménager une partie du rdc actuellement affecté en showroom automobile vers un espace de petite restauration2023
1 mChange of useRéaménager un showroom automobile vers un espace de loisir-réalité virtuelle au niveau du sous-sol, placer deux enseigne2023
2 mEnergy worksInstaller 4 pompes à chaleur sur le toit du bâtiment afin d'améliorer le confort climatique des usagers.2024
2 mHeavy renovation• Objet de la demande initiale : Restructurer le site D’Ieteren afin d’y redévelopper le bureau (21382m²), le commerce (2025
78 m09/PU/20441392026

Other nearby cases : 09/PU/1837003, 09/PU/1968107, 09/PU/1963357, 09/PU/1845350, 09/PU/1936004, 09/PU/2016492, 09/SFD/1822938, 09/AA/1848645, 09/PU/1827570, 09/SFD/1810173, 09/PU/1839792, 09/PU/2042883, 09/PU/1898517, 09/PU/2009234, 09/PU/2025904, 09/PU/2039664, 09/PU/1953021, 09/PU/1833392, 09/PU/1836903, 09/PU/1981102, 09/PU/1979245, 09/PU/2043431, 09/PU/2043432, 09/PU/1913346, 09/PU/2007802