Rue des Champs Elysées 98
Ixelles · 09/IPETMP/1928719 · Permis d'environnement temporaire
Rue des Champs Elysées 98, Ixelles: operation of installations. Case octroyé, lodged on 12 January 2024. The decision was notified on 1 February 2024, 20 days after lodging.
Asbest werken| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 12 January 2024 | date the file was received |
| Decision notified | 1 February 2024 | 20 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 25 m | Split into dwellings | mettre en conformité la division de l'immeuble en cinq logements, le remplacement des menuiseries en façade avant, la co | 2021 |
| 25 m | Extension or raising | transformer un immeuble notamment mettre en conformité le studio au sous-sol et le duplex 3e étage, le remplacement des | 2023 |
| 36 m | Split into dwellings | diviser une maison unifamiliale en deux logements, réaliser des aménagements intérieurs avec travaux structurels, isoler | 2025 |
| 45 m | Tree felling | abattre un arbre à haute tige : un tilleul | 2024 |
| 47 m | Roof | mettre en conformité l'agrandissement des 5 lucarnes existantes et le changement du revêtement de toiture, ainsi que réa | 2021 |
Other nearby cases : 09/PU/1892920, 09/PU/1990292, 09/PU/1892362, 09/PU/1925583, 09/PU/1835845, 09/PU/1864821, 09/GOU_PU/1926573, 09/PU/2001203, 09/PU/1967204, 09/PU/1901334, 09/PU/2038432, 09/PU/1990651, 09/PU/1953200, 09/PU/1998148, 09/PU/2006601, 09/PU/1830802, 09/PU/1830349, 09/PU/1840515, 09/PU/1871598, 09/PU/2042845, 09/PU/1951198, 09/PU/2006606, 09/GOU_PU/1964868, 09/PU/1994243, 09/PU/1901000
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)