Boulevard du Triomphe Bâtiment BC (accès 2)
Ixelles · 09/IPETMP/1994782 · Permis d'environnement temporaire
Boulevard du Triomphe Bâtiment BC (accès 2), Ixelles: operation of installations. Case annulé, lodged on 14 July 2025. The decision was notified on 28 August 2025, 45 days after lodging.
Chantier amiante| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 14 July 2025 | date the file was received |
| Decision notified | 28 August 2025 | 45 days |
| Works started | 8 September 2025 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 37 m | Façade and windows | isoler par l'extérieur 2 façades et une partie du mur mitoyen | 2023 |
| 123 m | Subdivision | Modifier le permis de lotirn° 09/LPFD/587636 | 2024 |
| 123 m | New construction | Construire deux immeubles neufs sur le Lot 2/B du permis de lotir 09/LPFD/587636 comprenant un immeuble d'intérêt collec | 2023 |
| 129 m | Public space | Fusionner deux unités commerciales au rez-de-chaussée, modifier la disposition de locaux techniques, apporter des ajust | 2025 |
| 134 m | Merger of dwellings | Modifier le permis d'urbanisme 09/PFD/1697204 délivré le 13/09/2023 pour construire un immeuble sur le Lot 3 du permis | 2026 |
Other nearby cases : 09/PU/2033515, 02/PU/1896047, 02/PU/1942522, 09/PU/1989339, 02/PU/1860432, 02/PU/1974812, 02/PU/1900803, 02/PU/1965341, 02/PU/1948137, 02/PU/1957566, 02/PU/1893577, 02/PU/2003973, 02/PU/1833850, 02/PU/1914073, 02/PU/1970350, 02/PU/1860623, 02/PU/1828389, 02/PU/1863353, 02/PU/1972219, 02/PU/2001554