Avenue de l'Hippodrome 71
Ixelles · 09/IPETMP/582575 · Permis d'environnement temporaire
Avenue de l'Hippodrome 71, Ixelles: operation of installations. Case annulé, lodged on 28 September 2015. The decision was notified on 23 October 2015, 25 days after lodging.
Chantier amiante| Permit type | Permis d'environnement temporaire | |
|---|---|---|
| Status | Annulé | |
| Lodged on | 28 September 2015 | date the file was received |
| Decision notified | 23 October 2015 | 25 days |
| Works started | 9 December 2015 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Decision notified · Withdrawn
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Change of use | changer l'affectation d'un commerce avec logement vers un équipement médical (cabinet psychologie) | 2025 |
| 0 m | Energy works | mettre en conformité le placement de 2 unités pompes à chaleur dans une cour au sous-sol | 2025 |
| 0 m | Change of use | changer l'affectation d'un commerce avec logement vers un équipement médical (cabinet psychologie) | 2024 |
| 0 m | Energy works | Plaatsing van één grotere en één kleinere HVAC unit in binnenkoer op - 1 | 2025 |
| 19 m | Demolition and reconstruction | démolir et reconstruire une annexe avec toiture terrasse et mettre en conformité le prolongement du garage | 2023 |
Other nearby cases : 09/PU/1967695, 09/PU/1961803, 09/PU/1865367, 09/PU/1871348, 09/PU/1915360, 09/PU/1845985, 09/PU/1906970, 09/PU/2035673, 09/PFU/2033342, 09/PU/1984937, 09/PU/1825633, 09/PU/1969335, 09/PU/2012703, 09/PU/1954208, 09/PU/1973999, 09/PU/1959452, 09/PU/2033124, 09/SFD/1822935, 09/PU/1955759, 09/PU/1869881, 09/PU/1975727, 09/PU/1841202, 09/SFD/1844955, 09/PU/1869561, 09/PU/2008313
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)