Parc Tenbosch
Ixelles · 09/PFD/1704792 · Permis d'urbanisme délivré par le FD
Parc Tenbosch, Ixelles: tree felling. Case octroyé, lodged on 5 March 2019. The decision was notified on 28 March 2019, 23 days after lodging.
Abattre un arbre| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 5 March 2019 | date the file was received |
| Decision notified | 28 March 2019 | 23 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 37 m | Extension or raising | transformer et étendre une maison unifamiliale | 2022 |
| 47 m | Extension or raising | mettre en conformité le logement-triplex des +2, +3 et +4 notamment l’extension du +3, la rehausse de la toiture, la con | 2023 |
| 54 m | Public space | Restaurer des murs du parc Ten Bosch. Permis modificatif pour adapter la solution de stabilisation initialement autorisé | 2026 |
| 61 m | Demolition and reconstruction | mettre en conformité le profil de la toiture et le châssis de la lucarne droite, démolir des annexes, construire une nou | 2025 |
| 73 m | Other | Délai défini à défaut d'analyse de la complétude | 2021 |
Other nearby cases : 09/PU/1831076, 09/PU/1928611, 09/PU/1911980, 09/PU/1917142, 09/AA/1826133, 09/PFD/1834391, 09/PFU/2004547, 09/PFU/2013979, 09/PFU/1910175, 09/PFD/1831404, 09/PU/1849299, 09/PU/1915863, 09/PU/1986937, 09/PU/2007082, 09/PU/1959883, 09/PU/1895882, 09/PU/2023470, 09/PU/1893089, 09/PU/1968086, 09/PU/1834432, 09/PU/2002775, 09/PU/1801283, 09/PU/1934833, 09/PU/1834520, 09/PU/2026912