Rue de la Concorde 33
Ixelles · 09/PU/1693538 · Permis d'urbanisme privé
Rue de la Concorde 33, Ixelles: extension or raising. Case octroyé, lodged on 9 November 2018. The decision was notified on 15 July 2019, 248 days after lodging. The project creates 59 m² of housing.
transformer un immeuble à appartement, notamment étendre le rez-de-chaussée et rehausser le bâtiment en intérieur d’îlot| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 9 November 2018 | date the file was received |
| Public inquiry | 15 April 2019 – 1 May 2019 | |
| Consultation committee | 15 May 2019 | |
| Decision notified | 15 July 2019 | 248 days |
| Competent authority | Ixelles |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Change of use | changer l'affectation au rez-de-chaussée gauche de l'immeuble de bureau en un équipement d'intérêt collectif (cabinet pé | 2025 |
| 36 m | Split into dwellings | mettre en conformité le nombre de logements, la modification de la répartition et la réalisation des transformations str | 2022 |
| 36 m | Change of use | mettre en conformité le changement d'utilisation d'un espace commun au rez-de-chaussée en un appartement et d'un studio | 2024 |
| 48 m | Demolition and reconstruction | mettre en conformité la réalisation de travaux structurels non conformes au pu n°2018/107 notamment la démolition complè | 2026 |
| 53 m | Roof | Régulariser la modification de la verrière au quatrième étage et des travaux d’isolation du pignon gauche | 2024 |
Other nearby cases : 09/PU/1972564, 09/PU/1994028, 09/PU/1849667, 09/PU/1929242, 09/PU/1917197, 09/PU/2011481, 09/PU/1945142, 09/PU/1973269, 09/PU/1811264, 09/PU/1961170, 09/PU/1820381, 09/AA/2023355, 09/PU/1870284, 09/PU/1923818, 09/AA/1915707, 09/PU/1987215, 09/PU/1870063, 09/SFD/1801661, 09/PU/2026045, 09/PU/1965437, 09/AA/1925646, 04/PU/1975180, 09/PU/1994402, 09/PU/2001111, 04/PU/1849323
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)