Chaussée de Boondael 180
Ixelles · 09/PU/1786232 · Permis d'urbanisme privé
Chaussée de Boondael 180, Ixelles: extension or raising. Case octroyé, lodged on 14 May 2021. The decision was notified on 21 December 2021, 221 days after lodging.
construire un balcon en façade arrière| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 14 May 2021 | date the file was received |
| Public inquiry | 17 September 2021 – 2 October 2021 | |
| Consultation committee | 20 October 2021 | |
| Decision notified | 21 December 2021 | 221 days |
| Works started | 22 April 2022 | |
| Floor areas | — | not reported by the source |
| Competent authority | Ixelles |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 8 m | Extension or raising | mettre en conformité l'extension du bureau situé au rez-de-chaussée vers le sous-sol ainsi que le remplacement des menui | 2021 |
| 44 m | Merger of dwellings | mettre en conformité le rassemblement de trois logements en une maison unifamiliale et remplacer les châssis en PVC et | 2024 |
| 46 m | Façade and windows | transformer un immeuble à l'angle notamment isoler la façade arrière ainsi que le mur pignon côté gauche | 2025 |
| 50 m | Extension or raising | mettre en conformité l'aménagement d'une chambre au sous-sol et l'agrandissement de la cour anglaise | 2022 |
| 69 m | Heavy renovation | mettre en conformité la modification du volume arrière non conforme au permis de bâtir n°1952/206 | 2024 |
Other nearby cases : 09/PU/2003579, 09/PFD/1839616, 09/PU/2041419, 09/PU/1839429, 09/PU/1952894, 09/PU/1942112, 09/PU/2020359, 09/PFU/1869421, 09/PU/1860719, 09/PU/1847705, 09/PFU/1991025, 09/PU/1908680, 09/SFD/1828614, 09/PU/1844119, 09/PU/1830033, 09/PU/1896196, 09/PU/1870084, 09/GOU_PU/1930603, 09/PU/1928595, 09/PU/1948490, 09/SFD/1824550, 09/PFD/1828384, 09/PU/1995864, 09/PFD/1984362, 09/PU/2039538
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)