Rue Edouard Faes, Jette: new construction. Case octroyé, lodged on 25 March 2013. The decision was notified on 3 June 2014, 435 days after lodging. The project creates 1 480 m² of housing.

Construire un immeuble à appartements à l'angle de la rue Edouard Faes et de l'avenue de Levis Mirepoix
The application's own description, in its source language (FR). Source: Nova.
1 480
Housing floor area created
Key figures
Permit typePermis d'urbanisme – recours au Gouvernement
StatusOctroyé
Lodged on25 March 2013date the file was received
Decision notified3 June 2014435 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.