Granted
Avenue du Laerbeek 101–111
Jette · 10/IPE/594169 · Permis d'environnement
Avenue du Laerbeek 101–111, Jette: new construction. Case octroyé, lodged on 23 February 2016. The decision was notified on 28 April 2017, 430 days after lodging.
Nieuw animalarium (gebouw L) op campus| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 February 2016 | date the file was received |
| Public inquiry | 23 November 2016 – 8 December 2016 | |
| Consultation committee | 16 December 2016 | |
| Decision notified | 28 April 2017 | 430 days |
| Works started | 13 June 2019 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 159 m | Public space | Intégrer un nouvel aiguillage afin de créer un nouveau terminus, installer un sanitaire pour les conducteurs de tram et | 2023 |
| 165 m | Tree felling | Abattre deux Erables sycomores situés sur un talus densément boisé, à développement spontané. L’abattage d’arbres perme | 2023 |
| 203 m | Extension or raising | Construire un jardin d'hiver à côté du bâtiment d'entrée actuel, régulariser un hall de déchets et réarranger l'infrastr | 2022 |
| 205 m | Extension or raising | Extension de l'hôpital des enfants | 2023 |
| 212 m | New construction | Installer une construction temporaire pour accueillir la morgue pendant la durée des travaux. | 2023 |
Other nearby cases : 10/PU/1827567, 10/PFU/1945703, 10/PFU/1946407, 10/PFU/2034403, 10/PU/1869969
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)