Rue Léopold I 329
Jette · 10/PFD/549600 · Permis d'urbanisme délivré par le FD
Rue Léopold I 329, Jette: heavy renovation. Case octroyé, lodged on 6 October 2014. The decision was notified on 16 February 2015, 133 days after lodging.
Het verbouwen van het gemeenschapscentrum Essegem| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 6 October 2014 | date the file was received |
| Decision notified | 16 February 2015 | 133 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Tree felling | l'abattage d'un arbre à haute tige en zone de recul | 2025 |
| 43 m | Façade and windows | la régularisation de la pose de crépi sur isolant et du remplacement des menuiseries extérieures en façade avant d'un im | 2022 |
| 46 m | Extension or raising | la démolition et la rénovation du bâtiment existant (dénommé "Vieux Pannenhuis"). La construction d'une extension contem | 2024 |
| 48 m | Change of use | l'aménagement d'un garage et des pièces de vie à la place du bureau au rez-de-chaussée, la modification de la façade au | 2026 |
| 52 m | Change of use | la régularisation du changement d'affectation d'un commerce en un atelier de fabrication artisanal de pain accompagné d' | 2023 |
Other nearby cases : 10/PU/2013518, 10/PFU/1921854, 10/PU/1833739, 04/PU/2029999, 10/PU/1869778, 10/PU/1823267, 10/PU/1981583, 10/PU/1983988, 10/PU/2017212, 10/PU/1952901, 10/PU/1849415, 10/PU/1853147, 10/PU/2003368, 10/PU/2025448, 10/PU/1864311, 10/PU/1866762, 10/PU/1827482, 10/PU/1894386, 10/PU/1852190, 10/PU/1902537, 10/SFD/1926546, 10/PU/1968268, 10/PU/1908116, 10/PU/1799403, 04/PU/1939923