Granted
Rue du Korenbeek 37–43
Molenbeek-Saint-Jean · 12/GOU/668904 · Permis d'urbanisme – recours au Gouvernement
Rue du Korenbeek 37–43, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 23 January 2018. The decision was notified on 11 October 2018, 261 days after lodging. The project creates 1 224 m² of housing. It comprises 14 dwellings.
construire un immeuble de logements comprenant 14 unités et 12 emplacements de parking en sous-sol ainsi que démolir 8 boxes de garages et reconstruire 7 boxes1 224m²
Housing floor area created
14
Dwellings created
| Permit type | Permis d'urbanisme – recours au Gouvernement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 January 2018 | date the file was received |
| Decision notified | 11 October 2018 | 261 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)