Skip to content
Altaica Urban
Granted

Rue de la Colonne 21

Molenbeek-Saint-Jean · 12/IPE/1973234 · Permis d'environnement

Rue de la Colonne 21, Molenbeek-Saint-Jean: —. Case octroyé, lodged on 31 January 2025. The decision was notified on 20 March 2025, 48 days after lodging.

BX3071
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on31 January 2025date the file was received
Decision notified20 March 202548 days
Works started20 March 2025
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Decision notified · Granted
  3. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mTree fellingAbattre 8 arbres qui se trouvent à l´intérieur d´un ensemble de bâtiments appartenant au Logement Molenbeekois. S2023
9 mTree fellingl'abattage de 8 arbres situés au fond de la parcelle du bâtiments2022
40 mPublic spaceRéaménager de façade à façade la rue de la Borne et ses carrefours2022
42 mHeavy renovationStabiliser les maçonneries2022
70 mChange of usela régularisation du changement d’utilisation d’une impasse en commerce, du changement d’utilisation de l’atelier arrièr2023

Other nearby cases : 12/PU/1962539, 12/PU/1825714, 12/PU/1928219, 12/PU/2037545, 12/PU/1825308, 12/PU/1838465, 12/SFD/2042758, 12/PU/1984054, 12/PU/1934656, 12/PU/1935474, 12/PU/2034951, 12/PU/2013522, 12/PU/1822184, 12/PU/1867304, 12/PU/1834244, 12/PFU/1857211, 12/PFD/1985248, 12/PU/1998154, 12/PU/1868486, 12/PU/1930184, 12/PU/1840879, 12/PU/1961893, 12/PU/1823339, 12/PU/1926158, 12/PU/1838574

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)