Granted

Rue de la Colonne 15–21

Molenbeek-Saint-Jean · 12/IPE/456453 · Permis d'environnement

Rue de la Colonne 15–21, Molenbeek-Saint-Jean: operation of installations. Case octroyé, lodged on 5 March 2010. The decision was notified on 12 November 2012, 983 days after lodging.

Exploitation d'un immeuble de logements
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusOctroyé
Lodged on5 March 2010date the file was received
Decision notified12 November 2012983 days
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
10 mTree fellingAbattre 8 arbres qui se trouvent à l´intérieur d´un ensemble de bâtiments appartenant au Logement Molenbeekois. S2023
16 mTree fellingl'abattage de 8 arbres situés au fond de la parcelle du bâtiments2022
38 mHeavy renovationStabiliser les maçonneries2022
47 mPublic spaceRéaménager de façade à façade la rue de la Borne et ses carrefours2022
69 mChange of usela régularisation du changement d’utilisation d’une impasse en commerce, du changement d’utilisation de l’atelier arrièr2021

Other nearby cases : 12/SFD/1915870, 12/PU/2037545, 12/PU/1825308, 12/PU/1962539, 12/PU/1928219, 12/PU/1934656, 12/PU/1838465, 12/PU/1984054, 12/SFD/2042758, 12/PU/2034951, 12/PU/1935474, 12/PU/2013522, 12/PU/1822184, 12/PFU/1857211, 12/PU/1998154, 12/PFD/1985248, 12/PU/1867304, 12/PU/1834244, 12/PU/1840879, 12/PU/1838574, 12/PU/1844735, 12/PU/1868486, 12/PU/1930184, 12/PU/1871127, 12/PU/1976417