Chaussée de Ninove 278

Molenbeek-Saint-Jean · 12/IPE/459543 · Permis d'environnement

Chaussée de Ninove 278, Molenbeek-Saint-Jean: operation of installations. Case annulé, lodged on 1 September 2011. The decision was notified on 6 March 2012, 187 days after lodging.

156B1&30048B1
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'environnement
StatusAnnulé
Lodged on1 September 2011date the file was received
Public inquiry24 January 2012 – 8 February 2012
Decision notified6 March 2012187 days
Works started1 March 2012
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Works started
  6. Decision notified · Withdrawn

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
29 mExtension or raisingla régularisation de l’extension en façade arrière et de la transformation de la façade avant, au rez-de-chaussée d’une 2025
34 mExtension or raisingl'extension de l'appartement du rez-de-chaussée2021
57 mSplit into dwellingsdiviser une maison unifamiliale avec rez-de-chaussée commercial2023
57 mSplit into dwellingsaménager un studio (R+1) & un duplex (R+2 + sous-combles)2026
65 mTree fellingabattre 41 arbres à haute tige2024

Other nearby cases : 12/PU/1964535, 01/PU/1939352, 01/PU/2011558, 01/PU/1951737, 01/PU/1822240, 01/PU/1947718, 01/SFD/2002256, 12/PU/1992422, 01/ECO/1827341, 01/PU/2022873, 12/PFD/1826096, 12/PU/1823517, 01/SFD/1849926, 01/PU/1811421, 01/PU/1922013, 12/PU/1833986, 01/PU/2033497, 01/PU/2036487, 12/PFD/1846900, 12/PU/1832873, 12/PU/2040655, 12/PU/1866446, 12/PU/1994877, 12/PU/2019220, 01/PU/1938169