Chaussée de Ninove 997
Molenbeek-Saint-Jean · 12/IPE/489483 · Permis d'environnement
Chaussée de Ninove 997, Molenbeek-Saint-Jean: operation of installations. Case octroyé, lodged on 4 July 2013. The decision was notified on 10 April 2014, 280 days after lodging.
Permis d'environnement pour la ferme "Claes"| Permit type | Permis d'environnement | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 4 July 2013 | date the file was received |
| Decision notified | 10 April 2014 | 280 days |
| Works started | 16 August 2016 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 60 m | New construction | Installer un pavillon temporaire pour l'école Paloke | 2025 |
| 60 m | New construction | Installer un pavillon temporaire pour l'école Paloke | 2025 |
| 80 m | Public space | Réaménager la voirie de façade à façade, entre le boulevard Louis Mettewie et la rue Van Soust | 2023 |
| 88 m | Extension or raising | régulariser la profondeur au rez-de-chaussée et au 1er étage, une terrasse au 1er étage, des éléments de toiture à l'ava | 2024 |
| 88 m | Signs and advertising | placer un dispositif publicitaire de 17 m² de type Prestige Backlight retro-éclairé & avec passerelle sur pignon | 2026 |
Other nearby cases : 12/PU/1829456, 12/PU/1980905, 12/PU/1945844, 12/PU/1902045, 01/PU/1999631, 12/PFD/1849139, 12/PU/2022953, 01/PFU/1861564, 01/PU/2001479, 01/PU/2030107, 12/PU/1904288, 12/SFD/1960815, 12/PU/2040658, 01/PFU/1955108, 12/PU/2026543, 01/PU/1902709, 12/PFD/2044034, 12/PU/2042587, 12/PU/1966793, 01/PU/2008635, 01/PU/1947014, 12/PU/1913697, 01/PFU/2008309, 01/PU/2009204
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)