Rue de Birmingham 57, Molenbeek-Saint-Jean: operation of installations. Case octroyé, lodged on 5 June 2020. The decision was notified on 20 December 2021, 563 days after lodging.
exploitation d'un immeuble de logements| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 5 June 2020 | date the file was received |
| Decision notified | 20 December 2021 | 563 days |
| Works started | 16 December 2021 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Works started
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 60 m | Demolition and reconstruction | démolir le bâtiment rue de Bonne/rue de Birmingham, dépolluer les sols, reconstruire un nouveau bâtiment, ouvrir le mur | 2024 |
| 60 m | Demolition and reconstruction | 1/ démolir le bâtiment rue de Bonne/rue de Birmingham 2/ dépolluer les sols 3/ reconstruire un nouveau bâtiment 4/Ouvri | 2023 |
| 64 m | Demolition | Régulariser le démolition de bâtiments d'activité productive en intérieur d'îlot et en démolir d'autres en raison de leu | 2024 |
| 64 m | Demolition | Régulariser le démolition de bâtiments d'activité productive en intérieur d'îlot et en démolir d'autres en raison de leu | 2025 |
| 67 m | Façade and windows | le remplacement du portail existant d'un atelier en façade avant façade par un portail en verre | 2023 |
Other nearby cases : 12/PU/1915503, 12/PFD/1918425, 12/PU/1851572, 12/PU/1899389, 12/PU/1899145, 12/PFD/1917482, 12/PU/1914566, 12/PU/1895302, 12/PU/2013272, 12/PU/1994329, 12/PU/2010714, 12/PU/1985389, 12/PU/1997196, 12/PU/1933210, 12/PFD/1800155, 12/ECO/1800142, 12/PU/1936309, 12/PU/1934647, 12/PU/1938758, 12/PFD/2041104, 12/PU/1941967, 12/PU/1961435, 12/SFD/1987346, 12/PU/1928599, 12/PU/1957787
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)