Rue De Koninck 40

Molenbeek-Saint-Jean · 12/IPEPLP/1907311 · Prolongation de PE

Rue De Koninck 40, Molenbeek-Saint-Jean: operation of installations. Case octroyé, lodged on 4 July 2023. The decision was notified on 25 July 2024, 387 days after lodging.

exploitation d'un ensemble de bâtiments affectés des activités productives
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on4 July 2023date the file was received
Decision notified25 July 2024387 days
Works started11 August 2024
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
53 mPublic spaceRéaménager de façade à façade la place Jef Mennekens et la rue De Koninck.2024
71 mChange of usele changement de destination d'un bâtiment d'activités productives (R+2) en équipement de type lieu de culte (803m²), in2025
74 mTree fellingAbattre un arbre à haute tige (cerisier)2024
74 mTree fellingl'abattage d'un arbre à haute tige (cerisier)2024
108 mExtension or raisingl'extension du parking existant de 25 à 40 places par le déplacement de la façade du n°101, en intérieur d'ilot2023

Other nearby cases : 12/PU/1853175, 12/SFD/1969584, 12/PU/1922357, 12/PU/1942482, 12/PU/1971636, 12/LPFD/1838931, 12/PU/1995044, 12/PFD/1985655, 12/PU/1800653, 12/PU/2001555, 12/PU/1950957, 12/PFD/1861013, 12/PU/1987184, 12/SFD/2021901, 12/PU/1948811, 12/SFD/2006334, 12/PU/1810647, 12/PU/1833070, 12/SFD/1908885, 12/PU/1897568, 12/PU/1914994, 12/GOU_PU/1945101, 12/PU/1979895, 12/PU/1977312, 12/PU/1931772

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)