Granted
Avenue Joseph Lemaire 4A
Molenbeek-Saint-Jean · 12/IPEPLP/1934930 · Prolongation de PE
Avenue Joseph Lemaire 4A, Molenbeek-Saint-Jean: operation of installations. Case octroyé, lodged on 28 February 2024. The decision was notified on 13 February 2025, 351 days after lodging.
Exploitation d'un parking souterrain de 53 emplacements à deux niveaux et 2 chaudières au gaz| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 28 February 2024 | date the file was received |
| Decision notified | 13 February 2025 | 351 days |
| Works started | 28 February 2025 | |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 30 m | Façade and windows | la modification des façades avant et arrière | 2022 |
| 40 m | Merger of dwellings | regrouper 2 logements 2 chambres en 1 logement 4 chambres au 3e étage (13 à 12 logements) | 2022 |
| 126 m | Extension or raising | régulariser la fermeture de terrasse et la création d'une pergola au rez-de-chaussée | 2024 |
| 146 m | Split into dwellings | la division d'un appartement en 2 logements au 1er étage d’un immeuble à appartements (passant de 23 à 24 logements au t | 2022 |
| 154 m | Extension or raising | la régularisation de la construction d'une terrasse au niveau du bel-étage et l'abattage d'un arbre à haute tige | 2025 |
Other nearby cases : 12/PU/1833129, 12/SFD/2014688, 12/PU/1993874, 12/PU/1996484, 12/PFD/1993595, 12/PU/1905280, 12/PU/2000651, 12/PU/1927359, 12/PU/2028081, 12/PU/1854748, 12/PU/1914080, 12/SFD/1925015, 12/PFD/2014049, 12/PU/2016749, 12/PU/2004540, 12/PU/1851073, 12/PU/1858783
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)