Quai de l'Industrie 119
Molenbeek-Saint-Jean · 12/IPEPLP/489287 · Prolongation de PE
Quai de l'Industrie 119, Molenbeek-Saint-Jean: —. Case octroyé, lodged on 27 June 2013. The decision was notified on 5 August 2014, 404 days after lodging.
| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 27 June 2013 | date the file was received |
| Decision notified | 5 August 2014 | 404 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Demolition | Transformer un bâtiment de commerce de gros en centre de formation, salle de conférence et équipement sportif, démolir d | 2023 |
| 73 m | New construction | Transformer le site industriel « Aciers Wauters » en un ensemble mixte composé de 182 logements sociaux et privés, 1466m | 2024 |
| 112 m | Extension or raising | ART 126/1 : la transformation et l'extension d'une maison de commerce (commerce de voitures + 3 logements), la création | 2021 |
| 114 m | Extension or raising | la rénovation et l'extension sur 2 étages d'un atelier-entrepôt existant (158m² à 206m²) | 2023 |
| 115 m | Change of use | changement d'utilisation d'un atelier de découpe de viande en atelier de production et conditionnement de produits alime | 2025 |
Other nearby cases : 12/PFD/2013037, 12/PU/1966818, 12/PFD/2024567, 12/PFD/1860254, 12/PU/1960708, 01/LPFD/1854269, 12/PFD/1913614, 12/PU/1864092, 12/PU/1973686, 12/PU/1972450, 12/SFD/1945236, 01/LPFD/1854249, 12/PU/1901740, 12/PU/1907157, 12/PU/1978098, 12/PU/2006202, 12/GOU_PU/2043553, 12/PFD/1980146, 12/PU/1988696, 12/GOU_PU/2021853, 12/PU/1960147, 01/PU/2019492, 12/PU/2006138, 12/PU/2034625, 01/PU/1905585
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)