Chaussée de Ninove 255–273
Molenbeek-Saint-Jean · 12/IPEPLP/608172 · Prolongation de PE
Chaussée de Ninove 255–273, Molenbeek-Saint-Jean: operation of installations. Case octroyé, lodged on 11 August 2016. The decision was notified on 24 February 2017, 197 days after lodging.
verlenging van een mv voor het uitbaten van een doe-het-zelf winkel| Permit type | Prolongation de PE | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 11 August 2016 | date the file was received |
| Decision notified | 24 February 2017 | 197 days |
| Floor areas | — | not applicable to this type of case |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 67 m | Extension or raising | Modifier le permis d'urbanisme relatif à la construction d'un immeuble de 31 appartements (ref Urban: 12/PFD/623153), re | 2021 |
| 67 m | Other | wijziging aan vergunde stedenbouwkundige vergunning PU-37100 | 2021 |
| 74 m | Extension or raising | la régularisation de l’extension en façade arrière et de la transformation de la façade avant, au rez-de-chaussée d’une | 2025 |
| 75 m | Extension or raising | l'extension de l'appartement du rez-de-chaussée | 2021 |
| 98 m | Tree felling | Abattage de 41 peupliers italiens près de la zone intérieure | 2024 |
Other nearby cases : 01/AA/1962360, 12/PU/1992422, 01/PU/2024661, 01/PU/1901201, 12/PU/1832873, 12/PFD/1846900, 12/PU/1833986, 12/PU/1926167, 12/PU/1824049, 12/PU/2004081, 12/PU/1994780, 01/PU/1951737, 01/SFD/2002256, 12/PU/2019220, 01/PU/1947718, 01/PU/1822240, 01/PU/1939352, 01/PU/2011558, 12/PU/2040655, 12/PU/1866446, 12/PU/1994877, 12/PU/1838242, 12/PU/2029230, 01/ECO/1827341, 01/PU/2022873
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)