Rue Docteur Charles Beudin 24A

Molenbeek-Saint-Jean · 12/IPEPLP/645589 · Prolongation de PE

Rue Docteur Charles Beudin 24A, Molenbeek-Saint-Jean: —. Case octroyé, lodged on 20 July 2017. The decision was notified on 30 August 2018, 406 days after lodging.

Key figures
Permit typeProlongation de PE
StatusOctroyé
Lodged on20 July 2017date the file was received
Decision notified30 August 2018406 days
Works started30 September 2018
Floor areasnot applicable to this type of case

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Decision notified · Granted
  5. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
51 mDemolition and reconstructionRénover, démolir partiellement et changer l'affectation de bâtiments en intérieur d'îlot d'activités productives industr2022
63 mExtension or raisingIsoler les façades, rehausser la toiture du bâtiment bas (au centre), construire un abri vélos, remplacer les châssis, e2025
67 mNew constructioninstallation d'une cabine à haute tension d'une puissance nominale de 250 kVA à 1000 kVA2024
68 mExtension or raisingl'extension du parking de 24 à 40 places dont 23 emplacements couverts2022
68 mExtension or raisingl'extension du parking existant de 25 à 40 places par le déplacement de la façade du n°101, en intérieur d'ilot2023

Other nearby cases : 12/SFD/1908885, 12/PU/2044209, 12/PU/2001555, 12/PU/1950957, 12/PU/1970621, 12/PFD/1939711, 12/PU/1950679, 12/SFD/1965873, 12/PU/1922357, 12/SFD/1969584, 12/PU/2019973, 12/PU/1972576, 12/PU/1931772, 12/PU/1979895, 12/PU/1971636, 12/PU/1896595, 12/PU/1934154, 12/SFD/2006334, 12/PU/1948811, 12/PU/1977312, 12/PU/2027407, 12/PU/1995044, 12/PFD/1834827, 12/PU/1849861, 12/PU/1916377