Granted
Cour Saint-Lazare
Molenbeek-Saint-Jean · 12/PFD/145245 · Permis d'urbanisme délivré par le FD
Cour Saint-Lazare, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 30 September 2002. The decision was notified on 5 March 2003, 156 days after lodging.
Placer une cabine haute tension hors sol| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 30 September 2002 | date the file was received |
| Decision notified | 5 March 2003 | 156 days |
| Floor areas | — | not reported by the source |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)
