Rue de Berchem, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 14 February 2003. The decision was notified on 14 November 2003, 273 days after lodging.

Construction d'un nouveau bâtiment pour un bureau de pointage, accueil de la petite enfance et logements,
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on14 February 2003date the file was received
Consultation committee25 March 2003
Decision notified14 November 2003273 days
Floor areasnot reported by the source
Competent authorityBUP

Timeline

  1. Application lodged
  2. Consultation committee
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.