Granted
Rue de la Flûte Enchantée 30
Molenbeek-Saint-Jean · 12/PFD/1821342 · Permis d'urbanisme délivré par le FD
Rue de la Flûte Enchantée 30, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 28 October 2021. The decision was notified on 24 November 2022, 392 days after lodging. The project creates 168 m² of housing.
construire une salle de sport et un logement de concierge168m²
Housing floor area created
| Permit type | Permis d'urbanisme délivré par le FD | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 28 October 2021 | date the file was received |
| Public inquiry | 16 May 2022 – 15 June 2022 | |
| Consultation committee | 12 July 2022 | |
| Decision notified | 24 November 2022 | 392 days |
| Competent authority | BUP |
Timeline
- Application lodged
- Declared incomplete
- Declared complete
- Public inquiry opened
- Public inquiry closed
- Consultation committee
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 36 m | Tree felling | l' abattage d'un arbre à haute tige | 2022 |
| 142 m | Tree felling | abattre un arbre à haute tige | 2024 |
| 154 m | Extension or raising | modifier le PU-38417 par l'ajout d'un étage en recul pour l’ajout d’un logement (7 vers 8 logement) | 2023 |
| 154 m | Split into dwellings | la modification, sur base de l’art.102 du CoBAT, du permis PU-37.526 pour la division du 1er étage en 2 logements (immeu | 2022 |
| 157 m | New construction | construire un immeuble R+2+T de 5 logements et 2 emplacements de parking voitures ART.126: construire un immeuble R+2+ | 2024 |
Other nearby cases : 12/PU/1913009, 12/PU/1833163, 12/PU/1974525, 12/PU/1981362, 12/PU/1943716, 12/SFD/2029513, 12/PU/1947274, 12/PU/1871134, 12/PU/1824805, 12/PU/1854867
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)