Rue Dubois-Thorn 2

Molenbeek-Saint-Jean · 12/PFD/490980 · Permis d'urbanisme délivré par le FD

Rue Dubois-Thorn 2, Molenbeek-Saint-Jean: change of use. Case octroyé, lodged on 19 August 2013. The decision was notified on 19 March 2015, 577 days after lodging.

Aménager un bureau postal au RDC (changement d’affectation commerce > équipement). Remplacer deux menuiseries extérieures. Poser une enseigne sur la façade. Placer une rampe PMR.
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme délivré par le FD
StatusOctroyé
Lodged on19 August 2013date the file was received
Public inquiry9 December 2014 – 24 December 2014
Consultation committee6 January 2015
Decision notified19 March 2015577 days
Competent authorityBUP

Timeline

  1. Application lodged
  2. Declared complete
  3. Public inquiry opened
  4. Public inquiry closed
  5. Consultation committee
  6. Decision notified · Granted