Granted
Rue du Hoogbosch 108
Molenbeek-Saint-Jean · 12/PU/1760857 · Permis d'urbanisme privé
Rue du Hoogbosch 108, Molenbeek-Saint-Jean: façade and windows. Case octroyé, lodged on 23 September 2020. The decision was notified on 17 December 2020, 85 days after lodging.
le remplacement des menuiseries existantes en PVC blanc (porte d'entrée, porte de garage et châssis) d’une maison unifamiliale R+2 par des menuiseries en PVC gris| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 23 September 2020 | date the file was received |
| Decision notified | 17 December 2020 | 85 days |
| Works started | 6 July 2022 | |
| Floor areas | — | not reported by the source |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
- Works started
- event_works_ended
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 69 m | New construction | la construction d'un immeuble R+3 (3 logements) ART126: la construction d'un immeuble R+2 (2 logements + 1 parking voitu | 2024 |
| 75 m | Tree felling | l'abattage d'un arbre | 2022 |
| 152 m | Heavy renovation | Transformer une maison unifamiliale | 2024 |
| 153 m | Tree felling | Abattre 9 arbres dépérissants et présentant un danger pour les usager.e.s du bois Hauwaert | 2026 |
| 178 m | Public space | Aménager une plaine de jeux et d'un street workout dans le Parc Hauwaert | 2022 |
Other nearby cases : 03/PU/1897271, 12/PU/1868588, 03/PU/1845803, 03/PU/1965414, 03/PU/1868420, 03/SFD/1826210, 12/PU/1941839, 03/PU/1973678, 03/PU/1968218
Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)