Skip to content
Altaica Urban
Granted

Quai des Charbonnages 80–82

Molenbeek-Saint-Jean · 12/PU/1769725 · Permis d'urbanisme privé

Quai des Charbonnages 80–82, Molenbeek-Saint-Jean: change of use. Case octroyé, lodged on 18 December 2020. The decision was notified on 6 May 2022, 504 days after lodging. The project creates 64 m² of housing. It creates 2 134 m² of office space.

de bestemmingswijziging van de verdiepingen van een grote speciaalzaak naar coworkruimte (kantoor – 1411m² + 13 parkeerplaatsen) en de regularisatie van de inrichting van een parking in openlucht (27 parkeerplaatsen)
The application's own description, in its source language (NL). Source: Nova.
64
Housing floor area created
2 134
Office floor area created
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on18 December 2020date the file was received
Public inquiry25 May 2021 – 9 June 2021
Consultation committee22 June 2021
Decision notified6 May 2022504 days
Works started27 February 2023
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Declared incomplete
  3. Declared complete
  4. Public inquiry opened
  5. Public inquiry closed
  6. Consultation committee
  7. Decision notified · Granted
  8. Works started

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mExtension or raisingle projet concerne la modification du permis PU-37960 : la modification des façades, l'extension du patio, la création d2023
49 mChange of usele changement de destination et le réaménagement d'un atelier en bureau (514m²) au niveau du 2ème étage d'un bâtiment ex2022
58 mPublic spaceRéaménager l'intérieur de l'ilot entrela rue des Ateliers et le Quai des charbonnages en parc semi-publique, le nouveau 2021
78 mFaçade and windowsle placement en recul d'un portail de garage2023
78 mFaçade and windowsle placement en recul d'un portail de garage2023

Other nearby cases : 12/GOU_PU/1858012, 12/GOU_PU/1858021, 04/PU/1827309, 12/SFD/1838974, 04/PU/1855430, 04/PU/1894844, 12/PU/2031297, 12/PU/1811462, 04/PFU/1902612, 04/PU/1858599, 04/PU/1895510, 04/PU/1960104, 04/PFU/1959851, 04/PFD/1984651, 12/PU/1934886, 12/PU/1866975, 04/PU/1930212, 04/PU/1810464, 12/PU/1893652, 04/PU/1801590, 04/PU/1914697, 12/PU/1827238, 12/PU/1824023, 04/PU/1975468, 12/PU/1998437

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)