Avenue Brigade Piron 60, Molenbeek-Saint-Jean: extension or raising. Case octroyé, lodged on 28 April 2021. The decision was notified on 13 September 2021, 138 days after lodging. The project creates 15 m² of housing.
la construction d’une annexe arrière et le réaménagement intérieur d’un appartement 2-chambres situé au rez-de-chaussée d’un immeuble de rapport de gabarit R+3 comprenant 4 logements| Permit type | Permis d'urbanisme privé | |
|---|---|---|
| Status | Octroyé | |
| Lodged on | 28 April 2021 | date the file was received |
| Decision notified | 13 September 2021 | 138 days |
| Competent authority | Molenbeek-Saint-Jean |
Timeline
- Application lodged
- Declared complete
- Decision notified · Granted
These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.
Nearby permits
| Distance | Work type | Object | Date |
|---|---|---|---|
| 0 m | Other | modifier la zone de recul | 2026 |
| 0 m | Other | modifier la zone de recul | 2024 |
| 0 m | Other | modifier la zone de recul | 2025 |
| 30 m | Extension or raising | la régularisation des volumes annexes arrières au RDC et R+1 et des modifications de la façade avant, ainsi que l’ajout | 2024 |
| 30 m | Extension or raising | la surélévation d’un immeuble de rapport avec l’ajout d’un logement au R+3, la régularisation des modifications intérieu | 2023 |
Other nearby cases : 12/SFD/1949590, 12/PU/1935293, 12/PU/1942181, 12/PU/2032857, 12/PU/1901122, 12/PU/1800049, 12/SFD/1857554, 12/PU/1950339, 12/PFD/2001491, 12/PU/2019491, 12/PU/2021689, 12/PU/1826024, 12/PU/1991974, 12/PU/1897568, 12/PFD/1980898, 12/PU/1977605, 12/PFD/1824692, 12/PU/1937191, 12/PU/2000869, 12/PU/1987184, 12/SFD/2021901, 12/PFD/1948049, 12/PU/1810647, 12/PU/1800653, 12/PU/1923908