Skip to content
AltUrb
Granted

Boulevard Louis Mettewie 9–11

Molenbeek-Saint-Jean · 12/PU/1801587 · Permis d'urbanisme privé

Boulevard Louis Mettewie 9–11, Molenbeek-Saint-Jean: new construction. Case octroyé, lodged on 8 October 2021. The decision was notified on 24 January 2022, 108 days after lodging.

PERIME : la construction d'un local vélos (+/- 42m²) au niveau de la galerie au rez-de-chaussée d'un immeuble à appartements
The application's own description, in its source language (FR). Source: Nova.
Key figures
Permit typePermis d'urbanisme privé
StatusOctroyé
Lodged on8 October 2021date the file was received
Decision notified24 January 2022108 days
Floor areasnot reported by the source
Competent authorityMolenbeek-Saint-Jean

Timeline

  1. Application lodged
  2. Declared complete
  3. Decision notified · Granted

These dates come from the source record. Altaica Urban has been following this permit since 11 September 2026.

Nearby permits

Planning permit cases within 250 metres, last five years.
DistanceWork typeObjectDate
0 mRegularisationrégulariser l'utilisation et la volumétrie (as-built) de l'étage technique (22e niveau) d'un immeuble à appartement2023
92 mSigns and advertisingrégulariser un dispositif publicitaire de 2m² Villo! (MU.RBC.0811) 2025
92 mSigns and advertisingrégulariser un dispositif publicitaire de 2m² Villo! (MU.RBC.0811) 2025
120 mExtension or raisingrégulariser 17 fermetures de terrasses d'appartements situés dans le bâtiment Turquoise et Zircon pour étendre les cuisi2026
153 mFaçade and windowsremplacement de la porte d'entrée du bâtiment2024

Other nearby cases : 11/PU/2016313, 12/GOU_PU/1903154, 11/PU/1950770, 12/PFU/2003603, 12/PFU/1859005, 12/PFU/1821793, 12/PFU/1921685, 11/PFD/1998897, 12/PFU/1999605, 12/PFU/1822750, 12/PFU/2025674, 12/PFD/1945406, 12/PFD/2029609, 12/PU/1915875, 12/PFU/2009409, 12/PU/2010337, 11/PU/1825343, 11/PU/1950344, 11/PU/1917548, 11/PU/2014188

Source: Région de Bruxelles-Capitale – Nova (urban.brussels, Bruxelles Environnement, communes)